KNA demoed, removed and disposed of existing electrical equipment along with installing new electrical equipment for two separate rooms at a military base in Hawaii. This included the demo, removal, and disposal of an existing transformer, UPS, battery cabinet, maintenance bypass cabinet, UPS supported panelboard and distribution panel.

This project also included the installation of the following:

  • Transformer

  • UPS

  • Battery Cabinet

  • Maintenance Bypass Cabinet

  • UPS supported Panelboard and Distribution Panel

Additional load wiring and grounding were also necessary to finish all of the upgrades for this custom Data Center project. 